Creating Storage Units Manually
Use
When you create transfer orders for storage units manually, the same functions are available as those for creating transfer orders based on transfer requirements. You can
For information on how to create transfer orders when SU management is not active in your system, see
Creating Transfer Orders.Procedure
Creating homogeneous storage units
The system proposes both a destination storage bin and a destination storage unit. If the destination storage type is assigned to an ID point, the system creates the TO working item with the ID point storage type (see
Using an ID point and Example: Putaway using an ID point).Creating mixed storage units
You can also enter additional default information that is then valid for all items of the storage unit you are creating.
Choose
Preparation.Depending on the settings in Customizing, you may also need to enter a destination storage type that is SU-managed.
The system assigns the storage unit number and storage bin for the storage unit, unless they have already been entered manually.
On this screen you also have the option to choose Reset TO. This makes it possible for you to enter a new storage unit number and/or destination storage bin.
You can also use this procedure to create single homogeneous storage units. In this case, enter only one material item for the storage unit in the transfer order preparation screen.
Add materials to an existing storage unit
On the initial screen you must enter the SU number of the storage unit. You can also enter default information that is then used for all items of the storage unit you are extending. In addition, you must enter the movement type for the material to be added to the storage unit.
Again, you have the option of entering default information that will be used later in the transaction for each item to be added.
The system displays two tabs:
The Items to be added tab is used to enter the materials that you want to add to the SU. The Stock in SU tab lists the materials that are already in the SU.
Certain values displayed on this screen (for example, the destination storage bin) cannot be changed because they pertain to the already existing storage unit.
The system creates the working items for the transfer order.
At this point, you still have the option to choose Reset TO if you need to add more materials or correct the working items.