Start of Content Area

Procedure documentationResource Planning  Locate the document in its SAP Library structure

Prerequisites

If you want to carry out resource planning without adopting the standard planner profile SAPR&R, you must define your own planner profile and planning layout.

Procedure

To plan primary costs at resource level, proceed as follows:

  1. Select a planner profile for resource planning such as the standard planner profile SAPR&R.

To do so, in your application choose Planning Set planner profile.

  1. Choose Planning Cost element/activity input Change.
  2. Select a planning layout for resource planning.

To change existing plans or create new ones, choose Change. In the overview screen you can enter the fixed and variable plan consumption for a resource. You use a distribution key to distribute the plan values to the fiscal year periods. You can either select a standard distribution key or define your own. On the period screen, you can also distribute your period values manually to the individual periods.

If you have stored a price for the resource (see: Pricing) the system revaluates the consumption using this resource price (see also Revaluating Resource Planning )

For more information about planning and changing planning screens, see Executing Manual Planning and Techniques for Supporting Manual Planning