Goods Receipts: Example of an Appointment  Locate the document in its SAP Library structure

The following table is a simplified example of the data contained in an appointment:

 

Explanation of the data displayed

The data displayed

Document category and document number

Purchase order 4500004711

Warehouse number / door

001/18

Planned start and end date

From 10/17 to 10/17

Planned start and end time

From 11:00 to 11:45

Actual date

10/17

Actual start and end time

From 11:00 to 12:00

Reason for variance

Overdelivery

 

In the example, goods were received at door 18 (warehouse number 001) for a purchase order. The appointment not only contains the planned data (date and time) but the actual data.

The merchandise was delivered punctually on the correct date. However, unloading took 15 minutes longer than planned, as more merchandise was delivered than had actually been ordered. This difference and its cause are used in analyses.