| finiteness level (SCM-APO-MD) |
Controls which applications can schedule a resource finitely or infinitely.
A resource has the finiteness level 200. In the strategy settings for "Production Planning" (PP), the finiteness level until which a resource should be scheduled finitely is 100, while in the DS strategy profile for "Detailed Scheduling" (DS), it is 200. Therefore, the resource will be scheduled infinitely in PP and finitely in DS.