Settings for the Detailed Planning
Process
You have transferred the ATP Customizing from SAP R/3 to SAP APO.
During the Customizing transfer the system created a check mode in SAP APO for the SAP R/3 demand class of the planning strategy. In the field Production Type of the check mode you either choose the setting Standard (ATP check based on time series) or Characteristic Evaluation (ATP check based on PP/DS).
You add the check instruction for the business events A and AE:
Field |
Input Value |
Product Check |
First Step |
Start Production |
Availability Check Only, No Production |
In the check control of the ATP group that you have transferred from SAP R/3 you set the Consider checking horizon indicator for the business events A and AE.
You create a new PP planning procedure by copying the PP planning procedure 4 Planning in Planning Run and making the following settings:
1. In the product master, check that the check mode and the checking horizon have been transferred from SAP R/3.
2. Enter the PP planning procedure in the product master.