Function documentationR/3 Integration of Planned Orders with Interchangeable Components  Locate the document in its SAP Library structure

Use

Planned orders that you create in Supply Network Planning (SNP) can be transferred to SAP R/3. Product substitution orders, on the other hand, are not integrated with SAP R/3. Therefore, any product substitutions that you plan for an assembly with interchangeable components are not visible in SAP R/3. However, the substitute components have to be contained in the planned order by the time of order processing in SAP R/3 at the latest. Only Production Planning and Detailed Scheduling (PP/DS) provides the necessary functions for including substitute components in a planned order with interchangeable components. Therefore, if you wish to integrate product substitutions with SAP R/3, you have to use PP/DS.

Note

Note that PP/DS does not support manufacturer part number management (FFF classes) at component level.

Activities

Decide which of the following two cases applies to you and then perform the activities described:

·        You are already using SNP and PP/DS together and are using PP/DS to plan on a more detailed basis after SNP has been run. In this instance, after Supply Network Planning has been run, you generate PP/DS planned orders that you integrate into SAP R/3. Before transferring the planned orders to SAP R/3, use the relevant PP/DS functions to update the planned order components. This ensures that the substitutes are also visible in SAP R/3. For more information, see:

¡        Product Interchangeability in SNP-PP/DS Integration

¡        Product Interchangeability with Order Processing in SAP R/3

·        You have not used PP/DS as of yet, but would like to integrate product substitutions with SAP R/3. In this instance, follow this procedure:

...

                            a.      Set up the PP/DS master data, including PP/DS PPMs and resources, for instance. The master data settings that you make for PP/DS have to be identical to those for SNP.

                            b.      In SNP, plan on a multilevel basis (with all components included).

                            c.      Convert the SNP planned orders into PP/DS planned orders.

                            d.      In PP/DS, adopt the substitute components into the PP/DS planned orders.

                            e.      Transfer the PP/DS planned orders to SAP R/3.

For more information about steps c, d, and e, see the documentation in the above links.

 

 

 