Stable Forward Scheduling
You can use
this heuristic to carry
out multilevel finite scheduling in the
detailed scheduling
planning board and in the production planning
run, in order to create a feasible short-term production
schedule.
This heuristic uses the algorithm /SAPAPO/SFW_HEUR_FW_STABLE.
You use stable forward scheduling to resolve the following planning problems, across a number of production steps:
· Backlog
· Capacity overload
· Violation of minimum intervals
· Violation of validity intervals of orders
For more information about prerequisites and activities for using the detailed scheduling heuristics, see Detailed Scheduling Heuristics.