Function documentation Stable Forward Scheduling  Locate the document in its SAP Library structure

Use

You can use this heuristic to carry out multilevel finite scheduling in the detailed scheduling planning board and in the production planning run, in order to create a feasible short-term production schedule.

This heuristic uses the algorithm /SAPAPO/SFW_HEUR_FW_STABLE.

You use stable forward scheduling to resolve the following planning problems, across a number of production steps:

·        Backlog

·        Capacity overload

·        Violation of minimum intervals

·        Violation of validity intervals of orders

For more information about prerequisites and activities for using the detailed scheduling heuristics, see Detailed Scheduling Heuristics.

 