Transferring planned independent requirements from DP to PP/DS
Purpose
You must transfer planned independent requirements that you have created in Demand Planning (DP) to Supply Network Planning (SNP) and to Production Planning and Detailed Scheduling (PP/DS), so that you can plan the covering of planned independent requirements there, and if necessary, can create procurement proposals. To transfer the demand plan to PP/DS, release the demand plan to SNP. For the planned independent requirements that are within the
PP/DS horizon, you plan the receipts in PP/DS.
Outside the
Prerequisites
Process Flow
Release demand plan with mass processing
Release demand plan online
The release period must be the same on the PP/DS horizon and SNP production horizon.
For more information, see:
Demand Planning Process
Releasing the Demand Plan to Supply Network Planning
Integrating SNP and PP/DS