Mass Maintenance of Time Series
Key Figures
In Supply Network Planning (SNP), planning is
generally based on order key figures. However, in some areas, you can also use
time series key figures, for
defining
time-dependent restrictions for optimization-based planning, for
instance.
You can use this function to carry out mass maintenance of time series key figures, that is, you can select several key figures and planning objects, and either define the key figure values for individual periods, or for all periods.
You can also use this function to process time series key figures for Demand Planning (DP).
· Selection of Key Figures
You can select the key figures for a particular planning area and planning time period, as well as for particular planning objects. As when defining a planning book, you determine the planning time period and the period schedule lines, by entering a planning buckets profile and a planning start date. You can also shorten the planning time period further by entering a time period for maintenance.
You select
the planning objects with the shuffler, as in
interactive
planning. In addition to the standard planning objects, in this function,
you can also use the SNP aggregate APO –
Prod.Transport (a product on a transportation lane). The APO – PPM/PDS aggregate also includes the header
product for the production process model (PPM) or the production data
structure (PDS). If you select
Display Selected Objects,
· Definition of Key Figure Values
You can define key figure values for individual periods or for all periods. The options available are:
¡
Set Key Figure
Values: You can
define the values for the individual periods. You can use the distribution
function to distribute values over periods, as in interactive
planning.
¡
Change Key Figures: You can
define or change the values for all periods in the planning time period. You
can also determine, for example, that you want the system to add or subtract
specific values or percentages to (or from) existing values.
Note that values saved earlier or in liveCache are not displayed, but are overwritten by the new values.
...
1. Select Advanced Planning and Optimization → Supply Network Planning → Environment → Mass Maintenance of Time Series Key Figures from the SAP Easy Access screen.
2.
Select the
key figures as detailed above, and then select
Set Key Figures or
Change Key Figures.
3.
After
entering the values, select
(with tooltip Save) or
(in the Background). If you select the latter option, you carry
out the saving procedure as a background job.