  Creating a Break Point

Use

You can use this procedure to create a cost structure that deviates from the production structure.

Prerequisites

  • You have entered a distribution profile in the project definition.

  • You have assigned the individual work breakdown structure (WBS) elements of your project to one or more grouping WBS elements.

Procedure

  1. In Command , enter PEG03 .

    The Change View "Breakpoint Maintenance": Overview screen appears.

  2. Choose New entries .

  3. Enter the required data.

    You must name a WBS element or a network activity as the break point.

  4. Choose Save .

Result

You can use the break point you have created as a cost assignment element. The costs of a replenishment element are now assigned to the break point instead of to the WBS element that created the requirement.

Note Note

The break points determined are listed in the assignment overview to display the pegging results (transaction PEG01) (for more information, see Break-points ).

End of the note.