overlapping (PP)

Production Planning and Control (PP)

A means of reducing the lead time by starting the next operation before the current operation is finished.

The system calculates the operation start and finish dates in such a way that the overlapped operations can be processed without interruption. The system takes into account the minimum send-ahead quantity and the minimum overlap time.