| lead-time scheduling (PP-MRP) |
A function that calculates production dates and creates capacity requirements.
Lead time scheduling is performed using the routing. In this case, it calculates the start and finish dates and times of the operations.
In MRP, lead time scheduling can be performed using the times specified in the material master. In this case, it calculates the production start and finish dates, but does not calculate capacity requirements.