Backlog Rescheduling
You can use this heuristic to
reschedule the backlog in the production planning
run and in the
DS planning board;
that is, you can automatically reschedule the operations that lie in the past
in the
planning period to
the current date or in the future.
· You can only execute the heuristic for resources and not for products.
· If you want to execute the heuristic from the detailed scheduling planning board, you have to select the resource for which the backlog is to be rescheduled.
The current date and current time is the default for the earliest possible start date for the operations to be rescheduled. With the help of the offset time in the heuristic settings, you can shift the earliest possible start date into the past or into the future.
This heuristic uses the function module /SAPAPO/HEUR_RESOLVE_BACKLOG.
For more information about prerequisites and activities for using the detailed scheduling heuristics, see Detailed Scheduling Heuristics.