mode linkage (SCM-APO-MD)
|
Master Data (SCM-APO-MD)
The linking of modes of two related activities.
There are several options for mode linkage:
- Linkage of modes with identical names - The modes of the activities must
have identical names for linkage. The activities must also have the same number of modes.
- Linkage of modes according to the primary resource - Modes are linked
from two activities that are assigned to the same primary resource. In this case, the mode names are unimportant.
Example
- Linkage of modes with identical names:
- Activity 1 (mode abc)
- Activity 2 (mode abc)
The modes with identical names are linked for activities 1 and 2.
- Linkage of modes according to the primary resource
- Activity 1 (mode abc, primary resource 123)
- Activity 2 (mode def, primary resource 123)
- Modes with identical primary resources are linked.