Period in which an object is used in a particular context:
● Goods receipt or goods issue of a transportation unit (TU)
● A vehicle’s stay in the yard
● Loading or unloading process of a door
A shipping and receiving activity (S&R activity) is unique for each object and time.
You use shipping and receiving activities to uniquely identify vehicles, TUs, and doors for a particular time period, thus enabling unlimited use.
Each shipping and receiving activity has a unique identification (ID), planned time and actual time:
● Planned arrival period (such as 23.11.05 between 10 and 11 o’clock)
● Actual arrival (such as 23.11.05 at 10:30)
● Planned departure period
● Actual departure
A shipping and receiving activity can have one of the following states:
● Planned
● Active
● Completed
● Invalid (canceled)
Only one active S&R activity per object (vehicle, TU and door) is possible. The system considers this first of all when it executes activities for the respective object. Activities for planned and completed S&R activities are also possible, such as archiving or deleting.
Information about S&R activities in connection with the individual objects:
● S&R activities for vehicles
○ You or the system create a new planned S&R activity for a vehicle, when its arrival in the yard has been planned.
○ The status of the S&R activity changes from Planned to Active for a vehicle when the status of the vehicle changes to Arrival at Checkpoint.
○ The status of the S&R activity changes from Active to Completed for a vehicle when the status of the vehicle changes to Departure from Checkpoint.
● S&R activities for TUs
○ You or the system create a new planned S&R activity for a TU when its arrival in the yard has been planned, or when you or the system assign TU deliveries (inbound or outbound) at the very latest.
○ The status of the S&R activity changes from Planned to Active for a TU when the status of the TU changes to Arrival at Checkpoint. You can also change the status manually using the function Maintain Transportation Unit(/SCWM/TU).
○ The status of the S&R activity changes to Completed for a TU when the status of the TU changes to Departure from Checkpoint.
If you want to use a TU during its stay in the yard for both an inbound and an outbound process, you map this using two S&R activities. In this instance, you can use function /SCWM/TU to change the status of the completely unloaded inbound S&R activity from Active to Completed, and the status of the new S&R activity from Planned to Active, without having to post the arrival at or departure from the checkpoint.
● S&R activities for doors
○ You or the system create a new planned S&R activity for a door when you or the system assign a TU to the door.
○ The status of the S&R activity for a door changes to Active when the TU arrives at the door.
○ The status of the S&R activity for a door changes to Completed when the assigned TU leaves the door.