You can make settings for the structure and layout of the order progress report in two profiles.
Overall profile
When you call the order progress report, you must enter an
overall profile
Profile for Displayed Fields
Profiles for displayed fields
are assigned to the
overall profile
You define these profiles in Customizing for
Shop Floor Control
by choosing
In the overall profile you make the following settings:
Assignment of the profiles for displayed fields
Standard values for certain selection criteria:
Elements that are account assigned to the production order
You can use this indicator to determine whether purchase requisitions and purchase orders for external operations and also rework orders are displayed. These elements are directly assigned to the production order. They are shown by a placeholder material (empty material field) and a corresponding icon.
Elements outside the product structure
This indicator determines whether other elements that are account assigned to the order or WBS element are displayed in addition to the elements that are in the product structure of the selected product (or assembly).
For instance, you have selected a sales order for a pump. The order progress display then displays the product structure (shaft, rotor, casing etc.). A production order that is account assigned to the sales order with material Motor is only displayed, if the indicator is set.
For all materials outside the product structure, only the first hierarchy level is displayed. This is because the hierarchy cannot be determined here and relationships that possibly exist cannot be taken into account. All the materials outside the product structure are displayed below the product structure.
Number of hierarchy levels
This number determines how many hierarchy levels are initially read into the order progress report. When you are working in the report you can read in further hierarchy levels.
Display
options:
Normal or compressed layout
Display and length of material short texts
Conditions for
Exception Messages
(see
Progress Value Determination
)
In a profile for displayed fields, you specify which fields are to be displayed in the report and how long these fields are. For each profile, you can create one subprofile for material fields and one for element fields (production orders, purchase requisitions, planned orders). You assign this profile to the overall profile.