Use

The standard system includes planning layouts for all planning areas. You can use these standard planning layouts, copy and adapt them to your requirements, or create completely new planning layouts. The standard planning layouts are divided into two categories: Planning layouts permanently assigned to a planner profile and planning layouts not yet assigned to a planner profile. The unassigned planning layouts are required only for special situations. Before using these unassigned planning layouts, you must first assign them to the corresponding planner profile.

Standard planning layouts are supplied only in client 000. To use the planning layouts in other clients, you must import them into the given client. You should execute this import after each release upgrade. For more information, see Customizing for Controlling under ControllingGeneral Controlling Preparation for Production Start Transporting System Settings Transport Settings for Planning Import Standard Planning Layouts

The standard planning layouts are protected. They cannot be changed. To create your own planning layouts with a similar structure to a standard planning layout, first copy the standard planning layout under a different name and then change the copy.

Integration

A list of standard planning layouts with brief descriptions is provided below.

SAP supplies the following planning layouts:

Cost Element/Activity Input Planning

Planning layouts

Description

Assigned to Planner Profile

1 - 101

Activity-independent and activity-dependent primary cost element planning

SAP101, SAPALL

1 - 102

Activity-independent and activity-dependent activity input planning

SAP102, SAPALL

1 - 102P

Activity-independent and activity-dependent process input planning

SAPALL

1 - 103

Activity-independent cost and revenue element planning

SAP103

1 - 104

Activity-independent and activity-dependent secondary order cost planning

SAP104, SAPALL

1 - 104P

Primary and secondary order cost planning for business processes

SAPALL

1 - 161

Decentralized simplified planning of costs and revenues

SAPEASY

1 - 162

Centralized simplified planning of costs and revenues

SAPEASY

1 - 1R1

Resource planning

SAPR&R

1 - 1R1

Value-based dependency planning

SAPR&R

1 - 1R3

Quantity-based dependency planning

SAPR&R

Not assigned

1 - 151

Activity-independent cost planning in transaction currency

1 - 152

Activity-independent cost planning for four quarters

1 - 153

Cost element planning for two versions

1 - 154

Cost element planning with previous year figures displayed

1 - 155

Activity output (sender perspective) with receiver valuation

1- 156

Central planning of a cost element

1 - 157

Cost element plan/actual comparison

Planning layouts 1 - 151 to 1 - 157 are provided in addition to the planning layouts already included in the planner profiles.

Activity Type Planning

Planning layouts

Description

Assigned to Planner Profile

1 - 201

Standard activity type planning

SAP101, SAP102, SAPALL

1 - 201C

Centralized planning of activity types/prices

SAPALL

1 - 202

Simplified PP planning

SAP103

1 - 203

Activity type planning with actual price indicator, switching structure for cost component splitting

SAP104

1 - 204

Activity type planning with prices and additional attributes, such as predistribution of fixed costs

SAP101, SAPALL

1 - 261

Simplified price planning

SAPEASY

1 - 262

Centralized simplified price planning

SAPEASY

Statistical Key Figure Planning

Planning layouts

Description

Assigned to planner profile

1 - 301

Activity-independent statistical key figure planning

SAP101, SAP102, SAP103

1 - 302

Activity-dependent statistical key figure planning

SAP104

1 - 303C

Centralized statistical key figure planning

SAPALL

1 - 361

Simplified statistical key figure planning

SAPEASY

1 - 362

Centralized simplified statistical key figure planning

SAPEASY

Planning Layouts for Cost Element/Activity Input Planning

Activity-independent and activity-dependent cost element planning (1 - 101)

With this planning layout you can plan:

Activity-independent and activity-dependent primary costs (cost element category 01, 04)

Revenues (cost element category 11, 12)

Activity-independent and activity-dependent settlement costs (cost element category 21)

Credits from overhead (cost element category 41)

The following table provides examples of planning records in this planning layout that can be used individually or collectively.

Header

Period

Fiscal year

Version

Cost centers

 

Activity type

Cost element

Cost element categories

Business transaction

-

400.000

1

Activity-independent primary cost planning

-

800.000

11/12

Revenue planning

Production hour

400.000

1

Activity-dependent primary cost planning

-

655.000

21

Activity-independent planning of settlement costs

Production hour

655.000

21

Activity-dependent planning of settlement costs

-

661.000

41

Planning for credits from overhead

To use activity-dependent and activity-independent planning in one planning layout, proceed as follows:

Select Entry optional in the planning layout for the variable of the activity type group. This is the case for standard planning layouts.

In the initial planning screen, you must have:

Specified an activity type group including the initial value, or

Entered “*” for the activity type. This entry allows you to plan all activity types, including the initial value.

Activity-independent and activity-dependent activity input planning (1 - 102)

The following table provides examples of planning records in this planning layout that can be used individually or collectively.

Header

Period

Fiscal year

Version

Cost centers

Receiver act. type

Sender cost center

Sender activity type

Business transaction

-

4210

REP

Activity-independent activity input planning

Production hour

4210

REP

Activity-dependent activity input planning

Activity-independent cost and revenue element planning (1 - 103)

The following table provides examples of planning records in this planning layout that can be used individually or collectively.

Header

Version

Fiscal year

Period

Cost centers

 

Cost/revenue element

Cost element categories

Business transaction

400.000

1

Activity-independent primary cost planning

800.000

11/12

Revenue planning

Activity-independent and activity-dependent secondary order cost planning (1 - 104)

Planning layout 1 - 104 was originally intended for secondary order cost planning. With this planning layout you can plan:

Activity-independent and activity-dependent primary costs

Revenues

Activity-independent and activity-dependent settlement costs

Credits from overhead rates

Activity-independent and activity-dependent secondary order costs

Activity-independent and activity-dependent secondary costs

The following table provides examples of planning records in this planning layout that can be used individually or collectively.

Header

Version

Fiscal year

Period

Cost centers

 

Cost element

Receiver acty type

Sender cost center Sender acty type

Cost element type Transaction

400.000

-

- -

1 Activity-independent primary cost planning

800.000

-

- -

11/12 Revenue planning

400.000

Production hour

- -

1 Activity-dependent primary cost planning

655.000

-

- -

21 Activity-independent secondary order costs

655.000

Production hour

-

21 Activity-dependent secondary order costs

634.000

-

-

41 Planning for credits from overhead

655000

4210 FST

21 Activity-independent secondary order costs

Local planning of total costs (1 - 161)

This planning layout allows you to plan locally (for each cost element) the total plan costs, without having to enter additional attribute values.

Centralized planning of total costs (1 - 162)

This planning layout allows you to plan centrally (for each cost center) the total plan costs, without having to enter additional attribute values.

Resource planning (1 - 1R1)

This planning layout lets you plan quantity-based primary costs.

The characteristics activity type, cost element, resource, consumption and costs are displayed together. The resource is a new characteristic that can be positioned anywhere in the layout: For example, in the header, in a lead column or in a value column. You can also include three new key figures in the planning layout for resource planning.

Price in the planned currency

Price in controlling area currency

Price unit

The system calculates as follows:

Fixed consumption quantity * Price = Fixed costs

Variable consumption quantity * Price = Variable costs

Total consumption quantity * Price = Total costs

Only the consumption quantities are displayed as ready for input in the planning layout.

It is possible to plan resources and cost elements in one planning layout. If the cost element and the resource are in the same lead column, and you enter only a resource, the system derives the cost element from the resource master data.

If you have executed detailed planning (by resource) for one or more cost elements, the system accumulates the costs below the cost element at resource level. These costs can then be used, for example, for distribution, assessment or plan cost splitting.

Value-based dependency planning

You use this planning layout for value-based planning of primary costs. You can add the following new key figures to the planning layout for value-based dependency planning:

Dependency type

Dependency source type

Fixed dependency price

Variable dependency price

Dependency source quantity

The system calculates as follows:

Fixed dependency price * Dependency source quantity = Fixed costs

Variable dependency price * Dependency source quantity = Variable costs

Depending on the dependency type, the fields Fixed dependency price, Variable dependency price, Plan fixed costs, and Plan variable costs in the planning layout are ready for input.

Quantity-based dependency planning

This planning layout lets you plan quantity-based primary costs. The characteristics activity type, cost element, resource, consumption and costs are displayed together. You can also include three new key figures in the planning layout for value-based dependency planning:

Dependency type

Dependency source type

Fixed dependency quantity

Variable dependency quantity

Fixed dependency price

Variable dependency price

Dependency source quantity

Fixed plan consumption

Variable planned consumption

The system calculates as follows:

Fixed dependency price * Dependency source quantity = Fixed costs

Variable dependency price * Dependency source quantity = Variable costs

Depending on the dependency type, the fields Fixed dependency qty, Variable dependency qty, Plan fixed consumption, Plan variable consumption, Plan fixed costs, and Plan variable costs in the planning layout are ready for input.

Activity-independent cost planning in transaction currency (1 - 151)

You can use this planning layout to plan costs in transaction currency.

Activity-independent cost planning for four quarters (1 - 152)

This planning layout allows you to plan by fiscal quarter.

Cost element planning in two versions (1 - 153)

You use this planning layout to enter plan values for two different versions. The SAP system calculates the difference between the two values.

Cost element planning with display of previous year figures (1 - 154)

This planning layout lets you display the previous year plan values for costs and consumption, in addition to the current plan values. The SAP system calculates the difference between the two values.

Planning activity output from a sender perspective (1 - 155)

This planning layout allows you to plan sender outputs. From a sender perspective, you plan: How high is the activity output of the sender?

Central planning of a cost element (1 - 156)

You can use this planning layout to plan centrally the costs and consumption of a cost element for all cost center/activity type combinations. The “Cost element” characteristic is in the planning layout header, the “Cost center/activity type” characteristic is in the rows.

Plan/actual comparison for cost elements (1 - 157)

With this planning layout, you can plan activity-independent costs while displaying the actual values of a comparison year.

Planning Layouts for Activity Types/Price Planning

Activity type planning (1 - 201)

Planning layout 1 - 201 lets you plan activity types on cost centers or cost center groups. The planning layout value columns contain the following key figures:

Plan activity

Capacity

Cost element for the activity allocation

Fixed price

Variable price

Price unit

Equivalence number

Scheduled activity

Distribution key, Activity unit, Plan price indicator, Long text exists , and Average price are added to the value columns as attributes.

Activity type planning for the PP planner (1 - 202)

This planning layout contains only key figures and attributes relevant to production planning. This includes the following characteristics and attributes:

Plan activity

Fixed price

Variable price

Price unit

Plan price indicator

Distribution keys

Activity unit

Cost element for the activity allocation

Average prices

Long text exists

Activity type planning with actual price indicator and switching structure for cost component splitting (1 - 203)

In addition to key figures for activity type planning (see also 1 - 201) this planning layout has key figures and attributes which give you the following activity type planning options.

Plan output

Set an actual price indicator varying from the plan.

Specify a switching structure for cost component splitting

Activity type planning with different attributes (1 - 204)

In this planning layout you can plan activity types with the following attributes:

Predistribution of fixed costs

Plan price indicator

Actual price indicator

Price calculation with the periodic averages

Plan activity type category

Actual activity type category

Exchange rate type

Value date

Switching structure

Output factor

Long text exists

Allocation cost element

Simplified price planning (1 - 261)

This planning layout lets you plan total prices for each activity type. Available attributes are Price unit , Distribution key , and Long text exists .

Simplified centralized price planning (1 - 262)

This planning layout lets you plan total prices centrally. Available attributes are Price unit , Distribution key , and Long text exists .

Planning Layouts for Statistical Key Figure Planning

Activity-independent statistical key figure planning (1 - 301)

You can use planning layout 1 - 301 to plan a current and a maximum value. Available attributes are Distribution key , Unit , Key figure type and Long text exists .

Activity-dependent statistical key figure planning (1 - 302)

Planning layout 1 - 302 contains the same value columns as the planning layout for activity-independent key figure planning. It differs only in the lead columns. While planning layout 1 - 301 has only one lead column (statistical key figure), planning layout 1 - 302 has two: Activity type and Statistical key figure . With this planning layout you can plan activity-independent and activity-dependent statistical key figures.

To use activity-dependent and activity-independent planning in one planning layout, proceed as follows:

Enter Entry optional In the planning layout as the variable for the statistical key figure group. This is defaulted for standard planning layouts.

In the initial planning screen, you must have:

Specified a statistical key figure group that includes the initial value, or

Entered “*” for the statistical key figure. This entry allows you to plan all statistical key figure, including the initial value.

Simplified statistical key figure planning (1 - 361)

You can use this planning layout to plan a current value. Available attributes are Distribution key , Unit , Key figure type and Long text exists .

Simplified centralized statistical key figure planning (1 - 362)

This planning layout allows you to plan centrally (for each cost center) a current value. Available attributes are Distribution key , Unit , and Long text exists .