A confirmation documents the processing status of orders, operations, sub-operations and individual capacities. It is an instrument for controlling orders.
With a confirmation you specify
The quantity in an operation that was produced as yield, scrap and the quantity to be reworked
How much work was actually done
Which work center was used for the operation
Who carried out the operation
Exact confirmation shortly after completion of an operation is essential for realistic production planning and control.
The following business transactions can be executed via confirmations:
Updating order data (for example, quantities, activities, dates, status)
Backflushing of components
Automatic goods receipt (for one operation per order max.)
Capacity reduction in the work center
Updating costs based on confirmed data
Updating MRP-relevant excess or missing quantities in the order
In Customizing for
Shop Floor Control,
by choosing
you can set up the following:
update of the yield variance
Adjustment of the operation and component quantity for a yield variance
Trigger reprocessing function (see Trigger Points )
Update usage counter for equipment PRTs
You can enter confirmations for
An order
An operation
A sub-operation
An individual capacity in an operation
An individual capacity in a sub-operation
Note
Operations, sub-operations and individual capacities are generally dealt with the same way in the confirmation. Therefore, only confirmation of operations is described. However, any differences are pointed out.
You can confirm the following data:
Quantities
You can confirm the quantity produced, the quantity of scrap that has occurred and a rework quantity. (This function does not apply to sub-operations).
Activity data
You can confirm the activities performed, for example setup time or machine time. You can also enter forecast values for individual standard values. These are used for determining the remaining activities and capacity requirements.
The actual or planned evaluation of work can take place using a cost center (activity types assignment) or using a Business Process . For more information about the business process refer to Quantity Determination .
Dates
You can confirm when setup, processing or teardown were started or finished.
Personnel data
You can confirm the following data:
The personnel number of the employee who carried out the operation
The number of employees who carried out the operation
Work center
You can confirm at which work center the operation was carried out.
Posting date
A posting date is entered for every confirmation. The default value is today’s date You can however enter another date. On the basis of the posting period in which the posting date falls, the system determines the rate for settling activities.
Goods movements
You can enter planned and unplanned goods movements for every confirmation. For more information, refer to Goods Movements in Confirmations
Reason for Variance
If the actual values differ from the planned values due to unpredictable events (for example, machine breakdown), you can enter a key in the
Reason
field, which documents the reason for the variance.
Note
If you combine the reason for variance key with a user status, you can trigger a follow-on function automatically via the reason for variance (for example, sending a mail to the responsible MRP controller). You can combine reasons for variance with user statuses in Customizing. For more information, see Example: Linking a User Status with a Reason for Variance .
Update usage counter for equipment PRTs
The usage counter is updated in relation to the confirmed quantity for equipment PRTs that are assigned to the operation and for which a measuring point has been defined.
Long text:
You can enter a long text to describe a confirmation.