 Confirmation of External Services or External Material

Purpose

If you schedule external material or external services in service and maintenance orders, you use external procurement processing for their completion confirmation.

Note Note

There are companies, which also want to perform capacity planning for employees from external companies. In such a case, it is possible to create service or maintenance orders, in which you plan the required external capacity, in addition to the external procurement processing described here, which is processed by Purchasing. These orders are then confirmed regularly by the employees from the external company to break down the planned capacity. For these completion confirmations, the employees from the external companies can use the entry options described.

For this type of processing, a control key, which allows capacity requirements to be determined, must be assigned to the external operations.

See also:

Control Key

End of the note.

Process Flow

  1. Based on the purchase requisition generated in the order, a purchase order for a material or an external service is sent to a vendor.

  2. If changes, with reference to the materials/services ordered (for example, different dates or quantities), occur in the order owing to the planning and executing of maintenance work, the system automatically changes the quantities if you are using SAP Business Workflow in your system and have made the necessary settings for this.

    For more information, see Change of a Purchase Requisition .

  3. The delivery or the service performed is treated as a goods receipt and posted directly to the order for which the material or external service was requested. The order is therefore charged immediately for the goods receipt with the relevant costs.

  4. When the invoice is received, any changes to costs incurred are settled to the order.

Especially for External Services:

The service is valuated with the purchase order price and entered in the accounts of Financial Accounting. The order used to order the service is charged with this value.

After a goods receipt for an operation, which is to be executed by an external company, this operation automatically receives the status External operation partially delivered . The operation only receives the status External operation delivered when the final delivery indicator is set for the goods receipt.

In the order, on the external processing screen for the operation, you can see whether a goods receipt has been posted for the purchase order. You can see the goods receipt quantity posted in the field GR qty .

For more information about external services, see Order Processing (External Assignment) .