You use inspection operations to describe individual inspection steps in an inspection plan and to define the work center and the default values for an inspection.
The header data for the inspection plan is already defined in the system.
The master records used (for example, material master record, dynamic modification rule) must have been created and released in the system.
The unit of measure defined in the header of a reference operation set that is to be referenced is the same as the unit of measure in the existing inspection plan.
Call up the operation overview screen from the create or change transaction for the inspection plan .
Create the required operations. You can link to reference operation sets to simplify data entry.
Enter the following data in the operation overview:
Field |
What You Should Know |
|
You enter the operation number. You can overwrite the proposed value. |
The control key defines the business relevance of the operation. Make sure that the
|
|
|
You define the place where the inspection is to take place or the person responsible for carrying out the inspection. |
|
The standard text key provides a default for the description of an operation. This key simplifies data entry. |
|
You enter a short description of the operation. |
|
You define the base quantity for the material to be manufactured. The default values for the operation relate to this quantity. You can overwrite the proposed value. |
|
You define the unit for the material to be manufactured. You can overwrite the proposed value. |
Choose
Operation
and on the operation detail screen, enter data as required:
Field/Screen Section |
What You Should Know |
You define the place where the inspection is to take place or the person responsible for carrying out the inspection. You can overwrite the proposed entry for the plant. |
|
|
You define the qualification that must be held by the inspection personnel. |
|
You enter the recording view that is to appear when you confirm inspection results. |
|
You enter the reference and the type of valuation for the inspection point. If you have defined inspection points in the task list header, this is a required entry. You can overwrite the proposed entry. |
|
You enter the default key words (field names) for the user fields. |
To edit a long text for the operation, choose
Long text
.
Once you have edited the long text, choose
Continue
to return to the operation overview.
To check if the inspection plan is
consistent
, choose
Check
.
Save the data.
Note
The authorization for entering data at operation level is controlled by the authorization object for the characteristics contained in the task list.
Additional Functions on the Operation Overview/Operation Detail Screen
Function |
Pushbutton/Menu Path |
What You Should Know |
Editing the previous task list |
|
If there are several task lists available in the system that fulfill the selection criteria, you switch to the previous inspection plan on the list. |
Editing the next task list |
|
If there are several task lists available in the system that fulfill the selection criteria, you switch to the next inspection plan on the list. |
Displaying/Editing task list header |
|
You can switch to the header detail screen of the inspection plan. |
Deleting an operation |
|
You can delete a selected operation at any time. |
Creating a reference |
|
When you create an inspection operation, you can link to one or more reference operation sets . |
Displaying/Editing operation details |
|
On the operation detail screen, you can edit additional data for the inspection plan. |
Editing inspection characteristics in the operation |
|
You can switch to the inspection characteristic overview of the operation. |
Assigning test equipment to the operation |
|
You can switch to the production resources/tools overview of the operation. |
Displaying the task list overview |
|
If there are several task lists available in the system that fulfill the selection criteria, you switch to the list of these. |
Other inspection plan |
|
You can edit another inspection plan. |
Creating an inspection plan |
|
You can switch to the transaction for creating inspection plans. |
Changing an inspection plan |
|
You can switch to the transaction for changing inspection plans. |
Display inspection plan |
|
You can switch to the transaction for displaying inspection plans. |
Editing/Displaying material-task list assignments |
|
You can assign one or more materials to an inspection plan. |
Displaying/Editing operation overview |
|
From the operation detail screen, you can switch to the operation overview of the inspection plan. |
Displaying object overview |
|
You can display a hierarchical overview of all the objects contained in the inspection plan. |
Displaying the first operation |
|
If there are several operations available in the system that fulfill the selection criteria, you switch to the first operation on the list. |
Displaying the last operation |
|
If there are several operations available in the system that fulfill the selection criteria, you switch to the last operation on the list. |
Displaying data for production resources/tools |
|
If production resources/tools were assigned to the operation, you can display general, scheduling and administrative data for these resources/tools. |
Displaying data for the inspection characteristic |
|
If inspection characteristics were entered in the operation, you can display general, quantitative and qualitative data for these characteristics. |
|
The information saved in a profile serves as the default for fields that are used repeatedly, when you create and change task lists. |
|
Displaying the validity, change number and revision level |
|
You can display the validity, change number and revision level for the current inspection plan. |
Displaying other operation overview variants |
|
You can display your own operation overview variants that only show the columns you require. |
Creating, displaying or unlocking references |
|
You can link to reference operation sets, display these references and unlock them to make changes. |
Scheduling an inspection plan |
|
You can schedule inspection plans. |
Classification at operation level |
|
You can create a link to the classification system at operation level. |
Displaying consistency log |
|
You can display a log of the inspections that have taken place. |
Displaying the work center |
|
You can display the work center, at which the inspection is to take place and for which the appraisal costs are to be confirmed. |