You determine the capitalization ratios based on cost elements. Furthermore you maintain whether revenues are to be treated as reducing expenses (other revenue) or as actual revenue.
You can change this setting while the sy stem is in active use:
If you want to create new cost elements
If you change the capitalization ratios
If you change whether you can or cannot capitalize of cost elements
If you do not define the assignment depending on the results analysis key, the changes are valid as of the validity date for all construction sites.
If:
You have different capitalization needs for different construction sites
In future a change to the capitalizability should only be valid for new construction sites
you must define the assignment in relation to the results analysis key.
If you want to define a new assignment for new construction sites at a later point in time, you need to take additional steps. For more information, see Changing Assignments
In Customizing for
Project System
under
Revenues and Earnings
→
Automatic and Periodic Allocations
→
Results Analysis
→
Edit Results Analysis Keys and Version
→
Define Assignments for Results Analysis.
Assign the line IDs.
Do not assign input data to the line IDs (category U) created for the calculation of key figures for GCC and IAS valuation.
Valuation in line with German Commercial Code
Line ID |
Procedure |
---|---|
Costs that must be capitalized |
Assign the capitalizable actual costs, other revenues and planned costs to this line ID. Enter the line IDs in the column
|
Costs that cannot be capitalized |
Assign the actual costs that cannot be capitalized to this line ID. Enter the line IDs in the column
|
Revenue |
Assign all invoiced work completed (posted revenue) and planned revenues to this line ID. Enter the line IDs in the column
|
Received down payments |
To assign all received net down payments to this line ID, enter an “A” in the column
Net down payments are read automatically if the component
|
Valuation in line with IAS
Line ID |
Procedure |
---|---|
Capitalized costs |
Assign all actual costs, other revenues that do not count as invoiced services and the planned costs to this line ID. Enter the line IDs in the column
|
Revenue |
Assign all invoiced payments (posted revenue) and planned revenues to this line ID. Enter the line IDs in the column
|
Received down payments |
To assign all received net down payments to this line ID, enter an “A” in the column
Net down payments are read automatically if the component
|
Save your input.
To change the version-specific settings for the results analysis version proceed as follows:
a.
In Customizing for
Project System
under
Revenues and Earnings
→
Automatic and Periodic Allocations
→
Results Analysis
→
Edit Results Analysis Keys and Version
→
Maintain Results Analysis Versions.
b.
Select the results analysis version and choose
using the quick info
Detail
.
c.
Choose
Extended Control In
and select the indicator
Assignment for Results Analysis Key
in the screen area
Extended Control.
You must flag this indicator for the results analysis version if you want to use the assignment depending on the results analysis key.
d. Save your input.
Maintain the assignment.
a.
In Customizing for
Project System
under
Revenues and Earnings
→
Automatic and Periodic Allocations
→
Results Analysis
→
Edit Results Analysis Keys and Version
→
Define Assignments for Results Analysis.
b. Execute the assignment of the line IDs as for ”assignment independent of results analysis key.” Note that you additionally enter the results analysis key for each line ID. Assignments without a results analysis key are not taken into consideration when valuation is performed.
c. Save your input.