Show TOC

 Preparatory Tasks

Purpose

The following settings should be maintained by the project team when implementing Valuation of Semi-Finished Constructions.

Process Flow

Basic settings

Once the application is in active use, you can only change these basic settings after checking with your SAP consultant.

a. Defining Versions

b. Defining Results Analysis Keys

c. Defining Valuation Methods

d. Defining Line IDs and Updates

e. Additional Settings for Valuation of Semi-Finished Constructions

f. Posting Rules for Transfer to Financial Accounting

g. Defining Message Control

Changeable settings

Defining Assignments

This setting cannot be changed whilst in active use:

If you want to create new cost elements

If you change capitalization ratios

If you change the capitalization of cost elements