  Construction Progress Report

Purpose

You want to enter values for work completed and contract values.

  • The values for work completed which are entered into the construction progress report document the progress at the construction site independently from the values of work to be invoiced.

  • The contract values entered in the construction progress report indicate all expected planned revenues.

    Note Note

    In contrast, the remaining planned revenues from the key date up until end of construction are entered into the remaining plan .

    End of the note.

Process Flow

  1. In the construction progress report you enter values for work completed as total values from the start of construction until the key date. You also enter contractually defined contract values that were determined in the respective period and fiscal year for the recipient WBS element.

    For more information see Creating and Changing Construction Progress Report Activities and Displaying Construction Progress Report Activities .

  2. The system updates the data in Controlling (CO).

    For information see Updating Construction Progress Report Data .