 Changing Parallel Sequences

If you want to change the text for the sequence, the branch operation or the return operation , proceed as follows:

  1. Choose Start of the navigation path Goto Next navigation step Overviews Next navigation step Sequences. End of the navigation path

  2. The system lists all the alternative and parallel sequences that already exist in the production order.

  3. Select the parallel sequence that you want to change and choose .

The system branches to a screen where you can make the changes.

If you want to change the operations in a sequence proceed as follows:

  1. Choose Start of the navigation path Goto Next navigation step Overviews Next navigation step Sequences. End of the navigation path

  2. The system lists all the alternative and parallel sequences that already exist in the production order.

  3. Select the parallel sequence that you want to change and choose .

The system lists all the operations contained in the sequence.

For more information about maintaining operations refer to Changing Operation Data .