 Overlapping in Collective Orders

Use

You can maintain overlaps between orders in a collective order. During scheduling, the system creates overlaps between the last operation in the subordinate order and the operation in the superior order in which the components are required, according to the settings you have made. Only the minimum move time of the last operation in the subordinate operation is used in scheduling.

Prerequisites

For an order in a collective to overlap with a superior order, the following requirements must be fulfilled:

  • You must have set up the overlap parameters in the last operation of the subordinate order ( Overlap operation tab page)

  • You cannot enter an offset in the superior order for a component that is directly produced in the subordinate order.

An offset ( Offset field) is the time between the requirements date of the component and the basic finish date of the subordinate order. You maintain this in Component detail data on the General data tab page in the Relationship menu.