 Confirmation of Material Used

Use

You can confirm which materials and how many materials you have used to execute an operation. You can also enter the return of unused material to the warehouse.

The materials used can be as follows:

  • Unplanned materials

These are materials that were not included for the operation in the planning of the order, but which were required to execute it.

  • Planned materials

These are materials that were planned for the operation in the order, withdrawn from stock and used in executing the operation. These materials can be indicated in the order as backflushed (see below) by the planner.

  • Backflushing

Often materials, which are low-value, small parts but are nevertheless managed in inventory management, are planned for orders. To avoid making a separate posting for withdrawal for each of these materials, the planner has the option in the order of marking such materials as backflushed. This has the following effects:

  • Display and change functions for overall completion confirmation and collective time confirmation :

Backflushed materials arenot displayed. They cannot be changed by the person making the confirmation.

  • Display and change functions for individual time confirmation :

Backflushed materials aredisplayedin the material overview, even if the parameter All components has not been set. They can be changed by the person making the confirmation.

  • For backflushed materials, a goods withdrawal is posted automatically after the first partial confirmation of the operation, for which you have scheduled.

  • Backflushed materials are also cancelled in the case of a cancellation of a completion confirmation , for which they have been posted as withdrawn.

Integration

When the withdrawal is made, the system automatically creates a goods issue document in Materials Management.

Prerequisites

The material movements possible for an order type are defined in the Customizing for Plant Maintenance.

Planned materials are only displayed in the material list if the necessary setting has been made in your system in the Customizing for Plant Maintenance.

Features

You can enter used material in the following transactions:

  • Overall completion confirmation

Here you can enter material used for different operations in an order without switching screens.

If you use the button Data for the operation for the required operation in the time confirmation table, the system displays all the materials planned for the operation in the material table.

For more information, see Confirming Material Used .

  • Single entry

Here you must specify on the initial screen, for which operation in the order you want to confirm the material used.

For more information, see Confirming Material Used .

  • Goods movements in inventory management

For more information, see Entering Used Material Using Inventory Management .

See also:

Confirmation of External Services or External Material