 Assigning Production Resources/Tools to Operations

Prerequisites

A master record must have been created in the system for a production resources/tool (PRT). Depending on the PRT category, the following additional requirements must be met:

  • Materials, equipment, and documents must have been released for use as production resources/tools via their status

  • Production resources/tools with a PRT-specific master record (miscellaneous) must have been released for resource planning via their status

  • Production resources/tools with a material master record, a PRT-specific master record, or an equipment master record must have been defined for routings via their task list usage.

Procedure

  1. On the operation overview of the routing, select the operation to which you want to assign production resources/tools.

  2. Choose Start of the navigation path Goto Next navigation step Production resources/tools. End of the navigation path

  • If PRTs have already been assigned to the operation, the PRT overview of this operation appears.

Choose Start of the navigation path Edit Next navigation step New entries End of the navigation path and the category of the PRT you want to assign.

  • If no PRTs have been assigned to the operation, the dialog box for production resources/tools of the category Material appears.

If you want to assign a different PRT category, choose the corresponding function key.

  1. Enter the PRT key as well as the item number and the basic data for PRT assignment and choose Continue .

  2. If you want to assign more production resources/tools, choose Start of the navigation path Edit Next navigation step New entries End of the navigation path and the PRT category you want to assign. Then repeat step 3.

  3. If you have finished assigning production resources/tools, choose Back .

  4. Select the assigned PRTs on the PRT overview and enter additional data for the assignment as required:

  • To enter standard values, choose Start of the navigation path Details Next navigation step Prod.resource/tool Next navigation step General view. End of the navigation path

  • To enter usage dates, choose Start of the navigation path Details Next navigation step Prod.resource/tool Next navigation step Dates. End of the navigation path

  • To enter a long text, choose Start of the navigation path Goto Next navigation step Long text End of the navigation path .