You access Primary Cost and Revenue Type Planning:
By choosing
Directly from overall planning
.
Choose
and enter the following for planning:Enter the standard profile
SAP IM1
to plan primary costs
Enter the standard profile
SAP IM3
to plan revenues
Choose
On the
Change Planning for Cost Elements/ActyInput: Initial
screen
, enter the data required.
The entries you have just made on the initial screen are set automatically by the system from overall planning.
In the period screen, you can plan each internal order across cost elements for the periods of a fiscal year.
In the overview screen, you can plan each internal order per period by cost elements.
The structure of this screen depends on the combination of planning objects you entered on the initial screen. If, for example, you enter an individual internal order and an individual cost element, then the system only displays these two objects.
Save your planning values.
You can obtain the cost element planning value by doing the following:
Call up overall planning for your order or order group. The
Cost Element Planning
view displays the value from cost element planning.