 Cumulating Standard Values

Prerequisites

If the standard values of the suboperations are to be automatically cumulated to the main operation when you create the production order, you must set the Cumulation type key accordingly in the routing.

Alternatively, you can trigger the cumulation of standard values in the production order. A condition for cumulation is that you have maintained standard values at suboperation level.

Procedure

  1. Choose Start of the navigation path Logistics Next navigation step Production Next navigation step Shop Floor Control Next navigation step Order Next navigation step Change Next navigation step . End of the navigation path

  2. Specify the number of the order that you want to change.

  3. Choose .

The initial screen for production orders appears. You can see the tab for production order data.

  1. Choose .

You reach the operation overview.

  1. Select the operation for which you want to cumulate the standard values.

  2. Choose Start of the navigation path Operation Next navigation step Cumulate standard values End of the navigation path

Result

The standard values of the suboperations are added together and written to the standard values of the operation.