 Creating a Delivery Schedule for an RFQ

If the desired quantity is to be delivered according to a prearranged schedule, you can enter each desired delivery date (and time if you wish) in schedule lines (e.g. 20 pcs. on 5 May 1998 at 10.00 hrs., 30 pcs. on 6 May at 10.00 hrs., etc.). You enter this data in the delivery schedule for the relevant PO item.

  1. Select the desired item in the item overview.

  2. Choose Start of the navigation path Item Next navigation step Delivery schedule End of the navigation path .

The screen for entering schedule lines for the item appears.

  1. Enter the delivery date, the delivery time-spot, and the scheduled quantity for each delivery. You can specify the delivery date as a calendar day, week, or month.

The section Outline Agreements with Vendors contains detailed information on the subject of delivery schedules created under scheduling agreements.