Choose
and then .If you want to create the production resource/tool (PRT) for a certain date in the future, rather than immediately, choose
Enter the data on the initial screen.
Use a material type that allows you to maintain the
Production Resources/Tools
view. In the standard system, the material type
Prod.resources/tools
has been defined for this purpose.
Choose .
The
Select View(s)
dialog box appears.
Select the
Production Resources/Tools
view and, if required, views of other user departments in which PRTs are to be taken into account. Choose
Continue
.
The
Organizational Levels
dialog box appears.
Enter the plant to which you want to assign the PRT, as well as organizational levels and profiles if you have selected further views.
If you have specified on the initial screen that you want to copy from a reference, also enter the organizational levels from which the reference data is to be copied.
Choose .
The first view appears.
Enter data as required and choose the next tab page.
Repeat step 6 until you have maintained all views.
Note
By specifying the MM/PP status, you release the material for use as a production resource/tool.
After you have assigned the material as a production resource/tool to operations, you can no longer change the base unit of measure or the unit of issue.
Save the material.
See also:
LO - Managing Material Master Data
:
Creating Material Master Records
,
Changing Material Master Records