Show TOC

 Batch Handling in the WM/PP Interface

Use

For components to be handled in batches, you can specify the point in time at which batches must be determined within sales order processing.

Features

As batch determination must be very flexible in the order, the SAP system has four methods of controlling it. The control is linked to the material and is defined in the material master record in the view MRP 2, in the Batch entry field. The control indicator determines the following scenarios:

Control Indicator

Short Description

<Space>

The batches can be determined in goods issue posting.

< 1 >

The batches must be explicitly determined in the order before the order is released.

< 2 >

The batches must be entered in the order before posting the goods issue, but not necessarily before releasing. If you are working with pick parts, batches will be determined in the transfer order and the determined batches are then confirmed in the production order/process order via the transfer order confirmation. However, you must post the goods issue manually.

If there is no direct reference between the transfer order and the production order/process order (for example, with release order parts and crate parts) you must enter the batches in the production order/process order manually.

< 3 >

Batches are automatically determined when orders are released.