 Assigning PRTs to an Operation

You can assign different PRTs (production resources/tools) to the same operation, and also assign the same PRT to different operations.

1. Call up the required order in create or change mode.

2. Enter all the required data and choose the operation overview.

3. Select the operations to which you want to assign PRTs.

4. Choose PRT (production resource/tool).

The system processes the operations you have selected one after another. The following cases can arise:

  • Still no PRTs have yet been assigned to the operation:

The Change Order: PRT New Entries dialog box appears.

If you want to add another type of PRT, choose Equipment , Others or Document .

  • PRTs have already been assigned to the operation:

The Change Order: PRT List for Operation dialog box appears.

If you want to assign additional PRTs, choose Start of the navigation path Edit Next navigation step New entries End of the navigation path and then choose one of the following options: Material , Equipment , Others or Document . The PRT New Entries screen appears.

  1. Make all the necessary entries in the dialog box PRT New Entries and choose Copy .

  2. The system writes the PRT to the PRT List for Operation and the dialog box PRT New Entries reappears ready for input. You can now assign another type of PRT.

  3. After you have entered the last PRT which you want to assign in the dialog box, choose Continue .

  4. The PRT List for Operation screen appears with all of the production resources/tools which you have assigned.

  5. If you have selected additional operations, to which you want to assign PRTs, then choose Start of the navigation path Operation Next navigation step Next operation End of the navigation path .

  6. After you have processed all the required operations, return to the operation overview and save the maintenance order.