When you schedule a maintenance plan, the following conditions must be fulfilled:
The scheduling data is maintained.
The maintenance plan contains at least one maintenance item.
Task lists are assigned to the maintenance items.
In the maintenance planning menu , choose .
You reach the initial screen for scheduling a maintenance plan.
Enter the number of the maintenance plan you want to schedule, and choose
Continue
.
You reach the
Maintenance Schedule
screen.
To start the scheduling function, choose
.The system displays the field
Start of cycle
as ready for input.
Enter the date on which you want scheduling to start, and choose
Continue
.
The system automatically calculates the planned dates and call dates based on the maintenance packages and the scheduling parameters .
If necessary, you can cancel scheduling (see Canceling Scheduling ).
Save the scheduled maintenance plan.