 Complete Withdrawal in the Confirmation

Use

You use this function during confirmation in the DIMP system to remove current batches that are assigned to a production order by means of fixed peggingin SAP SCM. Complete Withdrawaltakes place regardless of which quantities you confirm and which transaction the components are assigned to.

Integration

You can only use this function in conjunction with SAP SCM 4.1. It is only available for production orders of order category 10. The following table shows the transactions with which you can use complete withdrawal:

Transaction Name

Transaction Code

Enter Time Ticket for Production Order

CO11 or CO11N

Fast Entry: Time ticket

CO1V

Create Time Event

CO19

Collective Entry: Time Ticket

CO12

Progress Confirmation for Prod. Create

CO1F

Create Production Order Confirmation

CO15

Confirmation: Display Requests

CO1L

Note Note

You cannot use complete withdrawal for collective orders in discontinued lines or for variable-size items, .

End of the note.

Prerequisites

  • In Customizing for Production you must make the appropriate settings to ensure the system does not automatically show all components in the confirmation , by choosing Start of the navigation path Shop Floor Control Next navigation step Operations Next navigation step Confirmation Next navigation step Define Confirmation Parameters. Ensure that the All Components indicator is not set under Goods movements on the Generally valid settings tab page on the order type details screen. End of the navigation path

  • In Customizing for Logistics – General you must assign a characteristic from the variant class of the material for manufacture to the abbreviation 300,by choosing Start of the navigation path Basic Settings for SAP for Mill Products Next navigation step Assign Characteristics for SAP for Mill Products. End of the navigation path

  • You must work with batch classification for configurable materials or material variants.

  • The configuration of production orders and components must include the valuated characteristic with the abbreviation 300 . Planning takes place in SAP SCM.

  • You have neither used batch determination in the production order nor manually entered a batch number in the reservation. The Backflush indicator must not be set for components in the production order.

Features

During confirmation in the DIMP system, the system automatically proposes the components from the fixed pegging in SAP SCM as goods issue items on the goods movements screen.The system adds the pegging data, such as entry quantity, storage location, batch and special stock identifier, to the reservation data. You can edit this data by changing the quantity. Alternatively, you can delete the whole item. If you reduce the withdrawal quantity for a proposed batch, the system undoes the fixing of this batch for the relevant requirement in SAP SCM, if there is a manual fixing pegging relationship.

Note Note

If you save the confirmation directly, without calling up the goods movement screen, the system automatically creates and posts the goods movement items for the complete withdrawal. If you have instructed the system to issue a warning or an error message by making the relevant settings in Customizing for Logistics – General under Start of the navigation path Basic Settings for SAP for Mill Products Next navigation step Define Attributes of System Messages End of the navigation path for the messages of the work area/SAPMP/PP_SFC_EXE_GM, the system issues the message as a termination message. This is the only way to ensure a complete rollback.

End of the note.