 Scheduling Based on a Key Date

If you create a monthly maintenance cycle (one month = 30 days) and have specified key-date scheduling, planned dates are calculated as follows:

Current Date

21. August, 1999

1st planned date

21. September, 1999

2nd planned date

21. October, 1999

3rd planned date

21. November, 1999

The planned dates always fall on a specific day of each month, in this example on the 21st of each month.

Note Note

You should not define a key date later than the 28 of a month.

End of the note.