Show TOC

 Evaluation in the Information System

Use

You use this function to analyze costs and revenues arising from transfer prices.

Prerequisites

You can only evaluate costs and revenues arising from transfer prices using the profit center valuation. You specify this valuation in the selection screen for accessing reports. You can only specify the valuation if the parallel valuation has been activated in the controlling area.

The table below shows where you select the valuation in the reports.

Report

In the Selection Screen

Hierarchy Report

Additional parameter: Valuation

Cost element report

Additional parameter: Actual valuation

Line item reports

Choose Start of the navigation path Extras Next navigation step Actual valuation End of the navigation path

Features

You can only evaluate costs and revenues from transfer prices using the profit center valuation. The profit center valuation shows the actual costs, in addition to the transfer prices. The system does not display costs and revenues from transfer prices in the legal valuation.

You can evaluate transfer prices in standard reports or you can define your own.

Note Note

The structure overview does not include the costs and revenues from transfer prices unless you are using version 0 in the profit center valuation.

End of the note.

Evaluation at Profit Center Level

To evaluate costs and revenues from the point of view of the profit center manager, choose a database profile which includes the Profit Center project view. You must first maintain the group name for the profit center relevant to the project in the project view

Note Note

Higher-level profit centers display the costs and revenues for all the profit centers subordinate to them.

End of the note.

See Project Information Syste m and Selection Criteria and Representation .

Selection Using Subprojects

If you define transfer prices across subprojects, you can use dynamic selections to restrict data selection. For the data to be evaluated correctly, you must select the dynamic selections indicator in the database profile.

See Profiles in the Information System and Making Selections .

Authorizations

To ensure that those responsible for subprojects see only the costs and revenues relevant to them, you must assign authorizations at profit center level.

Standard Reports

We deliver the following standard reports:

  • Report 12TFP1: Transfer Prices: Service Recipient

The report shows a project with transfer prices, from the point of view of the contractor.

  • Report 12TFP2: Transfer Prices: Service Provider

The report shows a project with transfer prices, from the point of view of the ordering party.

Defining Your Own Reports

If you use your own reports, you must include the valuation in the general report selection. The table below shows the required variables:

Hierarchy Report

Variable 0VT

Cost element report

Variable G-VALK

Line item reports

The system updates the line item records for transfer prices to the CO activities KFPP (plan), KFPO (commitment), and KFPI (actual). You can restrict the line item evaluation to these activities by means of a display variant and appropriate filters.

You cannot evaluate planned line items for the transfer price agreement unless you manage CO version 0 in profit center valuation.

Example

The graphic below illustrates the example we will now examine.

You agree a transfer price of $5000 between WBS elements P1.1.1 and P1.1. $1000 has already been allocated. The profit center valuation shows the following values:

WBS Element

Planned Costs

Commitment

Actual Costs

P1

$5000

$4000

$1000

P1.1

$5000

$4000

$1000

WBS Element

Planned Revenues

Actual Revenues

P1

$5000

$1000

P1.1

$5000

$1000

P1.1.2

$5000

$1000

In WBS element P1.1.2, you plan costs of $4500 for the agreed services. The profit center valuation now shows the transfer prices, along with the costs planned.

WBS Element

Planned Costs

Commitment

Actual Costs

P1

$9500

$4000

$1000

P1.1

$9500

$4000

$1000

P1.1.2

$4500

 

$1000

If you are only authorized to display costs and revenues for profit center 1, the system displays the following values:

WBS element

Planned costs

Commitment

Actual Costs

P1

$5000

$4000

$1000

P1.1

$5000

$4000

$1000