 Specifying a Priority

Use

By assigning a priority to a notification, you can specify the importance and urgency of the notification.

Prerequisites

You have defined priorities in Customizing for the Plant Maintenance and Customer Service application components. You can define an interval for performing the notification for each priority.

Example Example

For example, priority 1 can mean: Execution is to start 2 hours after creating the notification and is to be finished within 2 days.

End of the example.

Procedure

  1. Call up the notification in create or change mode.

  2. Enter the required priority on the tabstrip Notification in the field Priority and choose Continue .

  3. The system calculates the required start and end of the maintenance notification in the background based on the definition of the priority, and enters these dates in the relevant fields.

    If you want to see the newly-calculated dates, call up the scheduling overview by choosing Start of the navigation path Goto Next navigation step Schedule overview End of the navigation path .

    When you release the notification, the system also calculates the dates for the tasks. This is done on the basis of the factory calendar. The dates for the tasks are displayed on the tabstrip Tasks .

  4. Save the data.