This process describes how you create a complete maintenance plan, which you can then schedule in order to generate maintenance call objects (for example, maintenance orders).
You create a maintenance plan and enter a maintenance plan category when creating it. You have the following options:
○ Creating a Single Cycle Plan
○ Creating a Time-Based Strategy Plan
Creating a Performance-Based Strategy Plan
Creating a Multiple Counter Plan
Creating a Maintenance Plan for Service Procurement
○ Creating a Maintenance Plan for an Outline Agreement
You enter the necessary data for the maintenance item.
There must always be at least one maintenance item assigned to a maintenance plan. If there are still older maintenance plans without maintenance items in your system, proceed as follows:
Call up the selection screen to change the maintenance plans.
Set the
Without
indicator under
Maintenance Items Assignments
.
Assign a maintenance item to the maintenance plans found.
You assign a task list to the maintenance item. This assignment is optional for single cycle plans. You have the following options:
You create a task list in the maintenance plan. For a strategy plan, you assign maintenance packages to the operations of the task list.
You assign an existing task list.
You assign further technical objects to the maintenance item if necessary using the
Object list
tab page (see
Object List
).
You assign additional maintenance items to the maintenance plan if necessary. You can:
Create a maintenance item in the maintenance plan
Assign maintenance items to a maintenance plan
You maintain the scheduling parameters .
You save the maintenance plan.