Use

You need to download data to the subsystem to carry out checks in the subsystem. Downloading is not necessary for PDC data transfer. The following checks can be carried out at the subsystem level:

  • Existence checks for operations

  • Quantity checks

Prerequisites

Operations that are to be transferred to the subsystem must be suitable for PDC. This means that,

  • The PDC active indicator has to be set in the order-dependent parameters (for each order type, plant).

  • The work center of the operation has to be assigned to a subsystem via Subsystem Grouping ( Basic Data tab , Subsystem pushbutton). You carry out this assignment in work center maintenance.

Features

In the initial download , the operations from the production orders that meet the corresponding conditions, are downloaded from the SAP system to the subsystem.

In the master data download the master data is downloaded to the subsystem, so that extensive checks can be carried out there. You can download the following data:

  • Work centers

  • Variations

  • Units of measure

  • Material-dependent units of measure

In the delta download all the operations that have been created since the last initial download are transferred to the subsystem.

Scheduling Background Jobs

You have to schedule the following programs for a download:

Task

Program

Menu Path

Initial download

SAPPPC21

Start of the navigation path Logistics Next navigation step Production Next navigation step Shop floor control Next navigation step Confirmation Next navigation step Subsystem Next navigation step Download Next navigation step Initial download. End of the navigation path

Master data download

SAPPPC22

Start of the navigation path Logistics Next navigation step Production Next navigation step Shop Floor Control Next navigation step Confirmation Next navigation step Subsystem Next navigation step Download Next navigation step Master Data Download End of the navigation path

Delta download

SAPPPC23

Start of the navigation path Logistics Next navigation step Production Next navigation step Shop floor control Next navigation step Confirmation Next navigation step Subsystem Next navigation step Download Next navigation step Delta download. End of the navigation path

You schedule the jobs in Customizing by choosing Cross-Application Components -> Plant Data Collection -> Production orders (PP, communication channel 2) -> Schedule background jobs for PDC .