Show TOC

 Urging Vendors to Submit Outstanding Acknowledgments

Use

You can require a vendor to submit an acknowledgment for each individual item of a purchasing document (PO, scheduling agreement, contract). This function allows you to select for expediting purposes purchasing documents for which no acknowledgment has yet been received.

In the case of purchase orders, the settings for the confirmation control key in Customizing are taken into account. In the case of contracts and scheduling agreements, the system checks only whether an order acknowledgment number exists at item level.

Prerequisites

  • The external messages have been set up in Customizing for Purchasing.

    You can also work with the standard settings. For further information, see Tips for Fast Message Determination Set-Up in the Implementation Guide (IMG).

  • Message records must have been created through master data maintenance ( Purchasing menu).

  • The Acknowledgment required indicator has been set in the relevant item of the purchasing document.

    See Confirmations from the Purchasing Viewpoint

  • The purchasing document involved must have previously been transmitted to the vendor.

Activities

You first generate messages for all purchasing documents for which acknowledgment expediting is necessary and then output these messages.

Generating a Message
  1. Choose Start of the navigation path <Purchasing document> Next navigation step Messages Next navigation step Monitor order acknowledgment. End of the navigation path

  2. Enter the criteria for selecting the purchasing documents to be checked with regard to outstanding order acknowledgments.

  3. If you select List non-transmitted messages , the resulting list will also contain documents for which an acknowledgment expediter has already been generated but not yet outputted.

  4. If you run the reminder program in the background, you must select Generate and save messages. The system will then generate and save the messages directly. The output list is for information purposes only.

  5. Start of the navigation path ChooseProgram Next navigation step Execute End of the navigation path .

    You will see the purchasing documents your vendor has not yet acknowledged.

  6. Select the documents for which you wish to issue order acknowledgment expediters.

  7. Save your selections.

    If you have set up the message determination process in such a way that the acknowledgment expediter is outputted immediately the application document is posted (transmission time-spot 4), you need not perform the following steps.

Outputting Messages Urging Submission of Overdue Acknowledgments
  1. To output the message, choose Start of the navigation path <Purchasing document> Next navigation step Messages Next navigation step Print/transmit End of the navigation path .

  2. Enter the same selection criteria as in step 2 and specify message type AUFB for acknowledgment expediters.

  3. Start of the navigation path ChooseProgram Next navigation step Execute End of the navigation path .

Procedure in System

The procedure depends upon whether you are working with or without a confirmation control key.

Without confirmation control key

The system suggests a purchasing document for expediting if there is no confirmation number (in the case of purchase orders and outline agreements), even if the vendor has already delivered part of the total quantity.

With confirmation control key

The system suggests a purchase order for expediting if the confirmed quantity is less than the ordered quantity.

The system takes into account the monitoring period you have defined in Customizing for Purchasing ( Start of the navigation path Confirmations Next navigation step Set Up Confirmation Control Next navigation step Confirmation Sequence End of the navigation path ) if the confirmation category (e.g. AB ) has been flagged as relevant to reminder/expediting.

The system suggests outline agreements for acknowledgment expediting if no acknowledgment number has been entered.