You can change an original order in the same way as a production order.
You cannot read master data in original orders.
As a rule, you can make the same changes to an original order that you can make to a normal production order.
You can never change combined operations and their components. The combined objects are only displayed for information purposes. If a component is added to a combined operation, this component is deactivated, but not automatically copied into the combined order.
Note
You can use this new component to affect the planned costs of the original order.
If you change the quantity in the original order , the change is passed on to the combined order. However, a quantity change in the combined order is not reflected in the original orders.
Recommendation
If you want to change the quantity in both the original order and the combined order, make the change in the original order.
If you make any changes to dates, you should take into account that at least one operation is dispatched. The remaining operations are then scheduled around the dispatched operation or operations using midpoint scheduling.
You can release the combined operations without affecting the combined order, but they are automatically released when the combined order is released.
Caution
You cannot technically complete, mark for deletion, or delete original orders, if the combined order is not technically completed, marked for deletion or deleted.
Note that the
Complete
status cannot be set in the original orders unless the
Deletion Flag
status has been set in the combined order.