Show TOC Anfang des Inhaltsbereichs

Vorgehensweisen Changing the ABAP Client for the UME After a Client Copy  Dokument im Navigationsbaum lokalisieren

Use

Use this procedure to switch to a new ABAP client for the user management engine (UME) after performing a client copy of the current client.

Prerequisites

      This procedure requires you to restart the SAP NetWeaver Application Server (AS) Java, so you should plan for the required downtime.

      The new client contains all users, roles, and user-role assignments of the original client, and you have not made any changes to these elements in the new client since creating the copy. If you have changed the client, you must change the AS ABAP back-end system for the UME. You must also use the procedure for changing the back-end system if you switch to a client copy created in a remote system.

For more information, see Changing the AS ABAP Back-End System for the UME.

Procedure

...

       1.      On the AS Java, start UME configuration.

For more information, see Configuring User Management.

       2.      Choose the ABAP Server tab.

       3.      Choose Modify Configuration.

       4.      Enter the new client value under Client.

       5.      Choose Test Connection.

If the test fails, go back and reenter the connection data and test the connection until you are successful. Make sure the AS ABAP is running and has access to your network.

       6.      Choose Save All Changes.

       7.      Restart the AS Java.

See also:

Client Copy

Ende des Inhaltsbereichs