Capacities can be created and edited in work centers (work center capacity)or independently (for example pooled capacities)
Capacity data is maintained on the following screens:
You can use Goto to switch between these screens.
As long as you do not save the capacity data, you can go back to the original state by
resetting a capacity .Initial Steps - Work Center Independent Capacity
The Initial screen appears.
The header screen appears
Initial Steps - Work Center Capacity
The Capacity Overview screen appears.
Capacity Overview
ScreenThe Capacity Overview screen is only available in work center maintenance
Here
If you do not specify a formula, no capacity requirements are calculated during capacity planning
Header
ScreenHere
Interval of Available Capacity Screen
Here
Available Capacity Profile
ScreenHere