Entering content frame

Component documentationQM in Production Locate the document in its SAP Library structure

Purpose

During production, it may be necessary for you to carry out a several individual inspections at different intervals or as a result of certain events. With the component QM in Production, you can process inspections during a production operation (while manufacturing discrete parts) or a process phase (while producing process goods).

Integration

The inspection characteristics in Quality Management (QM) are integrated in the work scheduling and production processing functions of the Production Planning (PP) component.

Features

Inspection Points

Using Structure link inspection points for an inspection during production, you can:

Note

It is recommended that you allocate inspection points with the same usage decision to partial lots. This allows you to manage partial quantities that differ in quality. In this way, you can monitor the production process continuously with respect to the inspection characteristics.

Inspection lot creation

When a production order is released, the system creates an inspection lot record to manage the inspection specifications and inspection results for all operations.

Recording inspection results for an inspection point

When you record inspection results in QM, you can also confirm the operations in the PP component. This can occur automatically. You can confirm the inspection point quantities in PP in the form of a partial or final confirmation. If you want to confirm additional data in production planning (in addition to the inspection point quantities and target activities), you can call up a dialog box for a detailed confirmation. In this dialog box, you can record such information as actual times or personnel-related data. You can also record defects.

Using control charts

Structure link Control charts are primarily used in inspections during production to monitor and control the production processes. The control chart can be used to detect disturbances in the process. You correct these disturbances by intervening in the process. You can use the control chart to determine whether the correction was successful.

Inspection completion

When you process partial lots and confirm an inspection point, the system automatically proposes a " Structure link usage decision" for each partial lot based on the inspection point valuation. You can change the proposed code within the predefined code group.

The usage decision for the inspection lot confirms that all inspections have been completed or that the production order has been completed from a QM standpoint. To make the usage decision for the inspection lot, you can define a job that makes automatic usage decisions at predefined intervals, once the orders have been completed.

Batch classification and quality certificates

Through the integration of the Structure link batch management functions, the system can transfer the inspection results for a partial lot to the batch and these results can subsequently be used to classify the batch. As a result, batches can be selected on the basis of inspection results in Sales and Distribution (SD). If the batch attributes were defined with the help of a material specification, the system uses the inspection results for the respective characteristics to classify the batches.

The inspection results can also be used to create quality certificates.

Proposed quantity for a goods receipt from production

The inspection point quantities for the last QM-relevant operation are proposed for the goods receipt posting for the order. Only the quantities confirmed to PP as a yield or rework quantities are taken into consideration.

See also:

Planning an Inspection During Production

Processing an Inspection During Production

 

 

 

Leaving content frame