Dividing the Work Breakdown Structure into Subprojects 
Use
If you use budgeting and availability control and want to enter a transfer price agreement, you must divide your work breakdown structure (WBS) into subprojects. You can form subprojects for standard structures and operative structures.
Prerequisites
You must first maintain identifiers for at least two subprojects. To call up structure planning, choose Logistics or Accounting ® Project System ® Basic data ® Project ® Special maintenance functions ® Work breakdown structure ® Subproject.
Procedure
This brings you to the initial screen for changing projects.
. This brings you to the Change Project: WBS Element Overview screen.
to save the assignments.Result
You have divided the project into subprojects and hence into different budget areas. Budgeting can now only be accessed using subprojects. When you access budgeting, you must specify a WBS element that has been defined as a subproject.