Entering content frame

Background documentation Status Information Locate the document in its SAP Library structure

The status information in the Implementation Guide helps you control project flow. It refers to both IMG documents and customizing projects.

It is always project-specific.

SAP provides the following status information:

SAP delivers status values in the standard. You can add your own status values.

The percentage complete is calculated from actual and remaining effort. You can enter planned and actual data for the start and end of a project.

You can assign internal and external employees or employee groups to a work step.

You can define keywords as project analysis search criteria.

You can make comments about the project.

For example to explain the project status.

 

All status information changes are logged. For every change, the SAP System generates a change document containing the following information:

You can display these changes with History.

The way in which the status information is handled depends on the display function which you chose.

If you display the Control function with split-screen, see Editing status information with split-screen.

If split screen is not set, see Editing status information without split-screen.

Leaving content frame