Procedure documentation Setting Posting Dates Locate the document in its SAP Library structure

Use

You can use this transaction to move the date forward on which postings are made in the system. SAP advises you to do this daily as part of the automatic end-of-day processing. 

You can set two different posting date values for each bank posting area:

·        Posting date for payment transactions

The system uses this date as the posting date default value for all postings in payment transactions that are initiated internally and externally (current payment transaction posting date).

If you set this date to the next day in the periodic tasks, you are making a posting cut-off. All postings from the payment transactions that are generated after the posting cut-off are posted on the new posting date unless you overwrite this during posting.

For more information about the prerequisites that a new posting date must meet, see the data element documentation (BKK_ACTPDT) for the posting date for payment transactions.

You can use the value date individually in payment transactions, irrespective of the posting date.

·        Posting date for end-of-day processing (closing postings)

The postings generated by the system in the closing tasks (such as account settlement and cash concentration) are posted on the posting date for end-of-day processing. This date cannot be later than the current posting date.
For more information about this date, see the data element documentation (BKK_ACTCDT) for the posting date for end-of-day processing.

Having two separate posting date values means that the postings for the payment transactions can enter the Account Management system on the new posting day, whereas the settlement postings are still posted on the old posting day. 

General Ledger Transfer

If the General Ledger Transfer component is active, both posting dates (payment transactions and end-of-day processing) must be later than the transfer key date for the transfer of the posting data to the general ledger. The posting date period, up to and including the transfer key date, must be flagged as Closed in the area menu as part of the periodic tasks for the general ledger transfer. Once a posting date has been flagged as Closed it can no longer have postings made on it in the Account Management system.

Set the posting date for payment transactions.

...

...

...

...

       1.      On the SAP Easy Access screen, choose Account Management ® Periodic Tasks  ® Set Posting Date ® Set Posting Date for Payment Transactions.

       2.      Enter the next highest posting date you require for the bank posting area in question.

Note 

Before entering a new date, you can display the current posting date by choosing Continue after entering the bank posting area.

Before you set an actual date, you can check the validity of the new date in a simulation run.

       3.      Choose Execute.

For more information about the report, see the report documentation in the system by choosing This graphic is explained in the accompanying text on the initial screen of the transaction.

You can have the posting cut-off executed automatically by the system during end-of-day processing.

For more information, see the Process Flow of End-of-Day Processing section of SAP Library.

Note

If the new posting date for payment transactions you have set is later than the current system date, you can still make the system accept your new date by setting the Set Posting Date in Future indicator. In Customizing, you can define the maximum number of days in the future within which the posting may be made.

Setting the posting date for end-of-day processing

...

...

       1.      On the SAP Easy Access screen, choose Account Management ® Periodic Tasks  ® Set Posting Date ® Set Posting Date for End-of-Day Processing.

       2.      Enter the next highest posting date you require for the bank posting area in question. Note that this posting date (end-of-day processing) must not be later than the current posting date (payment transactions).

Note 

Before entering a new date, you can display the current posting date by choosing Continue after entering the bank posting area.

Before you set an actual date, you can check the validity of the new date in a simulation run.

       3.      Choose Execute.

For more information about the report, see the report documentation in the system by choosing This graphic is explained in the accompanying text on the initial screen of the transaction.

You can have the posting cut-off executed automatically by the system during end-of-day processing.

For more information, see the Process Flow of End-of-Day Processing section of SAP Library.

Result

On the SAP Easy Access screen, the system displays the results of your change of date, including any error messages, in log format under Account Management ® Logs ® Posting Date.

 