Function documentationDate Maintenance

 

You can enter planned and actual dates, as well as restrictions for the campaign and the percentage of completion for the project.

You can also enter more specific dates.

Features

Entering Dates

You can enter planned dates for marketing projects under General Data. The system then automatically sets a constraint for the date. When you enter a start or end date, the system creates a restriction for this date (must begin on or must end on). If you enter both dates, the system sets a must begin on constraint on the start date, irrespective of whether the project is scheduled from the start or the finish.

You can also enter the actual dates and percentage of completion for a marketing project. Date checks are only carried out within a marketing project. You cannot check dates between marketing projects.