Scheduling and Schedule Strategies 
You can choose the scheduling strategy that you want to use for back end processing, in the service resource planning application.
You have set up the scheduling engine that you are using to implement service resource planning, in Customizing for Customer Relationship Management. You choose .
You have defined whether you are using liveCache or the resource planning application's built-in dispatcher, in Customizing for Customer Relationship Management. You choose .
If you use liveCache in your scheduling solution, you have determined scheduling strategies. To do so, choose in Customizing.
If you do not use liveCache, only the standard scheduling strategy is available. You can find more information in Customizing for Customer Relationship Management, by choosing .
You have entered a strategy, by choosing Settings in resource planning.
Scheduling using strategies is possible for service order items only.
If you are using an external scheduling solution, you have integrated the solution to the resource planning application.
Scheduling Engines for Service Resource Planning
Scheduling Engine |
Description |
Features |
|---|---|---|
Resource planning application using liveCache scheduler |
A memory-based database that includes multiple scheduling algorithms |
|
Resource planning application with built-in dispatcher |
Uses conventional techniques for data storage, and includes only one scheduling algorithm |
|
Connection to an external scheduling engine |
Supported by a third party, within connections via SAP NetWeaver XI (Is not supported by the resource planning application) |
The most important attributes of the scheduling engine are the scheduling rules, which define the overall planning strategy.
Scheduling Rules Supported by liveCache Dispatcher
Rule |
Description |
|---|---|
Find Slot |
The system attempts to schedule the demand in the next possible free time slot for a resource, in the planning direction. Resource utilization based on concrete and capacitive assignments is taken into account. If the scheduler is called with more than one resource, the system creates the assignment depending on the planning direction. For forward scheduling, the earliest time slot is used to create the assignment, whereas for backward scheduling, the latest time slot is used. |
Append Assignment |
The system attempts to schedule the demand after the last assignment of the given resource. This scheduling rule must be used with care, especially when you have assignments in the distant future (for example, maintenance orders). If the last assignment does not appear in the planning board, the appended assignment does not appear in it either. |
Infinite Planning |
The system schedules the demand on the required date, without accounting for the existing resource load. Only the availability of the resources is taken into account. This can be used as a fallback scheduling rule, if the Find Slot scheduling rule does not return a valid assignment. |
When you set up the strategies in Customizing, reference them within the resource planning application. In the Resource Planner Overview page, choose Settings. You see the Planning Settings page. In the Defaults area, choose the strategy from the Schedule Strategy dropdown list.